Delayed Tasks Summary
Last updated
Last updated
The Delayed Tasks Summary report helps identify the tasks which have exceeded their Expected End Dates.
To view this report, you can go to:
Home > Projects > Reports > Delayed Tasks Summary
The report is generated based on the Task Doctype.
Tasks have a date field called Completed On, which becomes visible when a Tasks status is changed to Completed.
If a task is marked as Completed and the Completed On field is set, then the delay is calculated as the difference between the Completed On and the Expected End Date.
If the Completed On field is not set, then the delay is calculated as the difference between the current date and the Expected End Date.
The chart shows the number of tasks that are On Track or Delayed based on the report generated after applying the filters.